We have tackled many large renovation and construction projects in the past, but this seems to be the biggest. There are many phases.
Also many sub-phases, of decisions and ordering supplies and demo of old parts of house, and moving things from one room to another and back again and living among chaos.
Phase one: Build new room off of living room to the enclosed stage. (projected completion July 17)
Phase two: Build new combination bathroom/laundry and dining area to the enclosed stage. (projected completion Aug. 3rd )
Phase three: Build new pantry and kitchen space to the enclosed stage. (projected completion Aug. 31st)
Phase four: New Roof (projected completion Sept. 7)
Phase five: Interior drywall (projected completion Sept 14)
Phase six: Arrange cabinetry in kitchen and install counters (projected completion Sept 21)
Phase seven: Flooring throughout house (projected completion Oct. 10)
Phase eight: Complete interior of kitchen/pantry (projected completion Oct 17)
Phase nine: Complete interior of bathroom/laundry (projected completion Nov. 2nd)
Phase ten: Complete new room off of living room (projected completion Nov. 14)
Obviously I HOPE that the projected completion dates are sooner not later and I'm able to do much of the simultaneous tasks to speed up the process. Ideally would be to complete all construction by Sept 7... but .... the workers require breaks and sleep and have other full time jobs and insist on being fed. If all goes well and Patrick takes a week off in August we should be able to shorten the projected dates quite a bit, but we'll wait and see.
Phase 1-4 must be completed before winter, along with building more cold frames, and cutting and stacking next winters firewood, as well as my projects of staining the barn, painting the exterior of the house, gardening and planting trees.
During Phases 5-10 I will need to stain the kitchen cabinets and paint all the new interior spaces
Next year.. build crannies and rebuild porch and back deck with back door. Plant more trees. Possibly relax a little. (and any other grand ideas I come up with over the winter)
So we're finishing up Phase one... here's out it's going so far:
Home Depot deliveries are... shake your head in bewilderment eventful.
They backed their own forklift into their flat bed truck... more than a few times. They almost drove over the lumber pile they had just placed on the ground. They drove over our pallet boardwalk and smashed one of the trampoline stakes. ... Oh.. and they forgot half the order so they came back later in the day.
They'll be back again in a week. We'll move the cars and put the chickens away before they come!

Progress is slow... for the observer. The crew claims that they feel like each day is productive.. but I can't paint yet or move things in... and there's a lot of noise.

The roof has really slowed things down.. There was excitement as concrete was poured and floors were built and then walls were put up.... and the roof... dismantling the old roof... repairing parts of the roof... .reconstructing the new pitch of the roof... laying the new roof and creating overhangs and gables...
Meanwhile the walls feel neglected and the causal observer sees nothing... because we refuse to go up on the roof.
Our local OSHA inspector is ruthless with his constant pacing the site with his clipboard and incessant questions. (granted they more often than not have to do with lunch orders and evening game or movie preferences... he's always hopeful they'll finish early... but they work until the sun goes down)
Well..
Mostly they work.
We do have a resident comic relief expert.
We are surrounded by construction.. supplies... noise.. and mess.
But it's happening.
We are learning as we go...
After haircuts is not a good time to wear a baseball cap while on the roof all day in the sun... His farmer tan lines are quite impressive.

The roof delivery guy is a great driver and crane operator and was a delight to do business with. He also had a really neat truck with an according folding top and a crane attachment.
Phase 1 is complete. The interior will not take too long and will be done here and there... higgeldy, piggeldy alongside Phase 2 etc...
Phase 2 is already behind schedule... the last delivery forgot crucial items and we are still waiting for them. We are both busy with other tasks and twiddling our thumbs in anticipation of staying on schedule.