Phase one: Build new room off of living room to the enclosed stage. (projected completion July 17)
Phase two: Build new combination bathroom/laundry and dining area to the enclosed stage. (projected completion Aug. 3rd )
Leaving Phase 1 incomplete to begin Phase 2 is difficult but I do understand the necessity of the order for exterior completion before winter. The other option is not to do so much in one year. That is not how I rumble! So, more chaos and eager anticipation.
Difficulties with Phase 2
- Our deliveries were missing essential material
- Our deliveries were delayed
- Plumbing!
- Rain, leaking in Phase 1 area since the roof is incomplete until Phase 2 is completed
- Damaged items had to be reordered, more delays
- Chimneys
Phase 2 compensated all its difficulties by providing helpers.
Caleb surprised us with a visit for his birthday. We poured concrete (he loves to work with concrete!). We also put together the beginning of the new floor for the laundry/bathroom.
Liam spent the day at our house. He thought it would be fun to see Duncan after an absence of 5 months. Not sure if he still thinks it was fun. They climbed under the house to put the vapor barrier on the underside of the new flooring.

Missionaries popped by to see us. They saw that we were doing a project and asked if they could come back to help. We weren't sure if they were serious but told them they can if they want. Saturday morning three of them, masked and wearing work clothes, knocked on the door. They were eager for something to do. They aren't allowed inside because of Covid and when it began to rain they sat on the porch to wait it out. I kept everyone supplied with fruit and cookies and water. For one, this was the first time using a drill, a chalk line and a power nailer. The walls were partially up and needed cross pieces put in. They also cleaned up all the demolition debris and then started putting up the plywood and the walls really took shape. It was Grandpa Ted's birthday so they lucked out and we served Voreniki and Root Beer floats.
Meanwhile... on the roof,
Derek hopped up on the roof a few times to help Duncan. He didn't last long after he sunburned terribly, even though he wore a hat. Long sleeves were found for him, but he wasn't eager to get back to working.
Between progress there was a lot of needed research and discussion. Plumbing issues to solve, roofing angles to get right... likely a lot more.. but it begins to sound the same to me and I had other things to work on. I had to empty the old pantry and make decisions on bathroom fixtures and lighting placement.
It's exhausting!
Listening to all the discussion and watching all the construction!
It does eventually all come together and begin to resemble a house.
Amusing moments of Phase 2
Since plumbing was out of commission while they ran the new drains, we created a temporary outhouse behind the barn in the ravine. We gave strict instructions DON'T use the toilet! The restrictions lasted a few hours. In a quiet moment in the evening we suddenly realized.. someone is in the bathroom. "Whittaker, DON'T FLUSH!"
"I forgot. Okay I won't flush."
A few minutes later he emerged from the bathroom... rushing water noises behind him... "Oh NO!.. I forgot. I flushed!"
No one wanted to be the one to let daddy know that when he returned from town with the plumbing fittings there was a surprise awaiting him under the house.
The theme song for the evening came from a little ditty Jim began singing.
Oh dear, what can the matter be...
7 old ladies locked in the lavatory
they've been gone Sunday til' Saturday
Nobody knew they were there....
Sunset over construction site
Phase two: Build new combination bathroom/laundry and dining area to the enclosed stage. (projected completion Aug. 3rd )
We didn't quite make the projected date of Aug. 3rd. On Aug. 14th, since Phase 2 was at yet another stalled point waiting for materials to be delivered, we began demolition on Phase 3. The materials arrived on the 20th. but Phase 3 was not at a stopping spot, so now there's two projects on the go for a bit. Hopefully Phase 3 will go quickly and get us back on track. The weather is cooperating.
Phase three: Build new pantry and kitchen space to the enclosed stage. (projected completion Aug. 31st) {or possibly Sept. 15th}